The chain begins with a development job. Spokane County employed Scarsella Bros. Inc. to construct out the Bigelow Gulch Street Challenge 5 on March 17, 2020, in accordance with the criticism. Scarsella subcontracted the paving to Poe Asphalt Paving, which completed on September 18, 2020. Poe’s subcontract required business common legal responsibility cowl of “$3,000,000 per prevalence” and “$3,000,000 annual combination (challenge particular),” and named the county and the contractor as further insureds – which means they may faucet Poe’s protection for claims tied to Poe’s work.Â